Ohio University Gordon K. Bush Airport taxiway rehabilitation update

Ohio University Gordon K. Bush Airport taxiway rehabilitation update
Airport Runway

July 2, 2019 - The Ohio University Airport was recently awarded a $1.5 million grant from the Federal Aviation Administration to rehabilitate the parallel taxiway and connectors.  Work is slated to begin July 8 with a completion date of August 5.  During the process a full runway closure will be implemented on Thursday, July 11 at 5:00pm through 7:00am Sunday, July 15.  A full runway closure will occur again the following Thursday, July 18 at 5:00pm through Monday, July 22nd at 7:00am.

Please continue to monitor NOTAMS for any changes and updates.